When you need a new connection
- A new-build or a property that has never been connected.
- The contract was cancelled (baja) by the previous owner or tenant.
- The supply was suspended for non-payment and the previous holder did not restore it.
- A renovation that changes the electrical installation, or a large increase in power.
How a connection works
- We check the supply point. We find the CUPS from the address and ask the distributor when and why the supply was stopped.
- We establish whether a certificate (CIE) is needed. For a new home it is mandatory; for an older one it depends on how long has passed and the condition of the installation.
- We calculate the distributor’s fees. Regulated charges apply to a connection and depend on the power and the situation.
- We choose a tariff and supplier, a good one from the start so you do not have to change later.
- We submit the application and follow it until the power is on.
Documents
- NIE, DNI or passport of the future account holder.
- Escritura, nota simple or rental contract.
- An electrical certificate (CIE), if one is needed.
- For some new-builds, a certificate that the home is fit to occupy (requirements depend on the region).
- IBAN for paying the bills.
Timescale and cost
If the installation is in order and the distributor needs no work on site, a connection can take a few days. If a new CIE or work on the network is needed, it takes several weeks. The cost is made up of the distributor’s regulated fees and, if necessary, an electrician’s services. We give you the figure before you submit the application.
Do not pay intermediaries who promise an “urgent connection for an extra fee”: distributor fees are set by the state and are the same for everyone.